Concrete batching plant parts
Concrete batching plant parts
1, sidewalk traveling speed: 24km / h to 24 km round-trip haul example to calculate.
2, concrete mixer truck charging time: HZS120 machine 1/6 hours / car, HZS90 machine 7/30 / hour.
3, concrete mixer truck unloading time: 5 minutes.
4, each completed a vehicle Concrete transport: HZS120 machine needs 1.25 hours, HZS90 machine needs 1.32 hours.
Can be shipped within 5,6 hour drive Number: HZS120 machine 6 × 1 / 1.25≈5 (car), HZS90 machine 6 × 1 / 1.32≈4 (car).
Completed within 6.6 hours pour concrete girder 320 m3, need to transport the car number: 320 × 1 / 6.5≈50 (car).
7, concrete mixer truck is equipped with transport should be considered because the pavement should leave some empty rate. HZS120 mixer station, the host capacity of 2m3, preferably with 9 m3 concrete mixer truck, in order to install four material. Haul about 12KM, be completed within six hours pouring concrete girder 320 m3, preferably with 10 to 11 concrete mixer truck.
8, HZS90 mixer station hosts a capacity of 1.5 m3, preferably with 8 m3 concrete mixer truck, in order to install five material. HZS90 + HZS120 stand mixer, preferably with 8 m3 concrete mixer truck, in order to install four material. Haul 12KM, within six hours to complete watering concrete beam 320 m3, preferably with 13 to 14 units of concrete mixer truck.
Inquiry
(Please write down the product model or any requirement) | |
E-mail: | |
Message: | |
Contact Information
E-mail:chris@concretebatchplant24.com
Tel: +86-371-65621392
Fax:+86-371-86616825
Add : No.14 Waihuan Road,New strict,Zhengzhou,China